STATES OF JERSEY

Energy From Waste Facility: Public Inquiry (P.136/2008) – comments
Presented to the States on 16th September 2008
by the Minister for Transport and Technical Services
STATES GREFFE
COMMENTS
Introduction
It is very unfortunate that the States are being asked
to debate this matter when the Assembly has already debated the question of
whether the preferred location should be La Collette instead of
Bellozanne. The Connétable’s report makes no mention of P.45/2006 “Solid Waste
Strategy: locations for proposed facilities”, which was a specific debate,
following extensive public consultation, to determine where this new facility
should be constructed. The States approved, by 32 votes, in favour of
La Collette as the most suitable location for the new Energy from Waste
Facility, this debate including drawings showing the full scale of the proposed
development.
Summary
1: There
is little or nothing at all that supports the request for holding a public
inquiry. The relevant time for consideration of whether a public inquiry was
necessary was at Outline Planning Stage as there clearly was a departure at
that time from the original 2002 Island Plan, albeit that the States had agreed
La Collette as the preferred location.
2: At
that time, the new Planning and Building (Jersey) Law 2002 had not come into
force, and it was for this primary reason that the Minister for Planning and
Environment concluded that it was not appropriate to hold a planning inquiry
under Article 12 of this Law.
Instead, as in previous decisions to depart from the
Island Plan, the States Assembly had been asked to take this major decision.
This decision was taken by the States in June 2006 (P.45/2006) following a full
public consultation process where all relevant drawings showing the full scale
of the facility had been provided to any member of the public attending these
meetings.
In addition, in October 2007 when the Outline Planning
Consent was granted, the drawings showing the re-designed facility, as designed
by Sir Michael Hopkins and Partners, were publicly available and were also
being used as part of the States Members’ briefing sessions for P.72/2008
“Energy from Waste Facility: establishment and acceptance of tender”.
The arguments regarding the appropriate level of waste
minimisation/recycling for the Island and those for or against Energy from
Waste as an appropriate solution to deal with the Island’s residual waste have
been debated by the States on 3 occasions: P.95/2005 “Solid Waste
Strategy”, P.45/2006 “Solid Waste Strategy: locations for proposed facilities”
and P.72/2008 “Energy from Waste
Facility: establishment and acceptance of tender”.
3: There
has been a 3 year period, between 2005 – 2008, for the
Environment Scrutiny Panel and their advisers and others to come up with a
suitable and proven alternative to the approved Energy from Waste
facility – they have not.
4: The
location at La Collette has been debated and agreed. Whilst the facility
is large, both the building and the surrounding landscaping have been designed
by architects of international repute. These highly acclaimed experts have gone
to extraordinary lengths to ensure that the quality of the design for the
building is very high and the landscaping, whilst in keeping with its location,
will do everything possible to screen the building. These will be 2 key factors
for the Minister for Planning and Environment to consider when he concludes the
reserved matters.
5: Further
delay to the project is unacceptable and seriously jeopardises the Island’s
ability to deal with its own waste.
6: The
cost of any delay to the Project will be very significant.
Comments on the Report
The Connétable’s opening remarks concerning the
Department’s refusal to supply certain documents to the Scrutiny Panel’s adviser
are simply wrong. This was clearly explained during the debate for P.72/2008 “Energy from Waste Facility: establishment and
acceptance of tender”, and specifically within the Department’s response
(R.43/2008 Rpt.) to the Environment Scrutiny Panel’s Report R.43/2008 “Environment Scrutiny Panel: Independent
Review – Planned infrastructure for implementing the Island’s Waste
Strategy and Consideration of possible alternative approaches”, which
was circulated to all States Members; but for clarity it is important for
members to have the full facts before them.
The Transport and Technical Services Department did
supply the information in question, relating to the way in which the overall
size of the Energy from Waste Facility was determined, to the Environment
Scrutiny Panel. It was the Panel that did not forward this information to their
advisers. Updated information that led the Department to recommend the smaller
plant was not available to the Department itself until just after the
Environment Scrutiny Panel adviser had published their report on 25th April
2008. This new and updated information was passed to the Environment Scrutiny
Panel and their adviser as soon as it was available.
The Connétable’s report outlines the requirement under
the Planning and Building (Jersey) Law 2002 for a public inquiry. For the
purpose of these comments, they will follow the same order as the Connétable’s
report in that matters relating to Article 12(1)(b) of the Planning and
Building (Jersey) Law 2002 will be dealt with first.
The Connétable is correct in stating that moving the
Energy from Waste (EfW) plant from Bellozanne to La Collette is a
departure from the 2002 Island Plan. Unfortunately, what the Connétable fails
to consider and comment on is that in 2006, the States considered P.45/2006
“Solid Waste Strategy: locations for proposed facilities”.
It was this very debate that concluded that a
departure from the Island Plan was appropriate for a number of reasons that
were outlined in the Report associated with that debate.
At the time of the debate on P.72/2008, consideration
of whether co-operation with Guernsey sending its waste to Jersey for disposal
in a new joint plant had been finalised and Members were aware that this option
had been discounted by the States of Guernsey.
To state that the decision to move from Bellozanne to
La Collette was as a result of a relatively late amendment to the Solid
Waste Strategy debate is misleading. The amendment from Deputy Fox
(P.95/2005 Amd.(2) “Solid Waste
Strategy (P.95/2005): second amendments”), which was also accepted by
the Environment and Public Services Committee, recommended the option of moving
the EfW plant from Bellozanne to La Collette and to bring back to the
States the fully worked options.
Following the Waste Strategy debate on P.95/2005
“Solid Waste Strategy”, much work was undertaken to evaluate La Collette
as a site. Before the matter was brought to the States in the form of P.45/2006
“Solid Waste Strategy: locations for proposed facilities”, public consultation
was undertaken in the form of public meetings with the Havre des Pas residents,
public meetings and a 2 day open public consultation event.
The decision to buy up properties within a certain
radius of the waste treatment plant at Bellozanne was relevant with regard to
the Bellozanne incinerator now, and remains so into the future, as there are no
current proposals for relocation of the Sewage Treatment Plant and other
industrial activities; therefore, it has little or no impact on the decision to
move the EfW facility from Bellozanne to La Collette.
The reference to the location of the EfW plant at
La Collette taking up valuable land for the development of the Island’s
light industry is again misleading. Referring to the Island Plan Drawing
No. 2-02/A clearly indicates which land on La Collette is to be
designated for the development of light industry. The location of the new
Energy from Waste Facility is not within this designated area and no land will
have been lost. Therefore all the references contained in the
Connétable’s report on pages 4, 5 and 6 are totally irrelevant.
At the time of Outline Planning Consent being granted,
one of the Reserved Matters was for the Transport and Technical Services
Department to demonstrate that the small area of land lost for the proposed
amenity space would be compensated by an equivalent area within the site. This
has been done and will be one of the matters for consideration by the Minister
for Planning and Environment when he considers the Reserved Matters.
Turning to Article 12(1)(a) of the Planning and
Building (Jersey) Law 2002, the Connétable states 6 reasons why
paragraph (1)(a) has relevance.
All 6 reasons have either been considered by the
States through P.95/2005 “Solid Waste Strategy”, P.45/2006 “Solid Waste
Strategy: locations for proposed facilities” or are being addressed as part of
the overall development for La Collette. Careful consideration has already
been given to the location for the EfW facility and whether it could have any
detrimental impact on future development.
Comment on Reason 1:
There is no denying that the Energy from Waste
incinerator is a large building. This has been clearly stated at all of the
many public meetings and States Members’ briefings on the Solid Waste Strategy.
At all of those meetings, drawings showing the full scale of the facility have
been on display, and to suggest that it is only a montage in a colour brochure
that has been used to show the full size of the plant is, once again,
completely wrong.
The size and location of the new incinerator has been
considered in architectural terms by the Minister for Planning and Environment
who has insisted that the building structure has to be to a design reviewed by
a leading firm of architects of international repute. To satisfy this
requirement, Sir Michael Hopkins and Partners, the architects involved in
transforming the Esplanade development into the new Waterfront Quarter, have
been engaged. They reviewed the original design and, through their involvement,
the building was re-designed from the original with a curved roof to one with a
more geometric form. This revised design was submitted formally as part of the
Outline Planning Application process.
To suggest that a public inquiry should be provided
with an honest assessment of what the proposed building will actually look like
is again misleading, as the drawings showing the building have been on public
display and have also been released to the media. The final design must be
approved as part of the Reserved Matters submission, which again involves
further public consultation. In any event, the planning application process
itself is a comprehensive variant of a public inquiry.
Although a section of the designated recreation area
stretching from Fort Regent to La Collette will be removed to accommodate
the new EfW incinerator, it is a relatively small section that will be fully
compensated for as part of the overall landscaping for the area. The linear
landscaping will still provide a screen from the east of the Island to the more
industrial complex of the La Collette II development site. It should
be noted that public access to the La Collette Area is now discouraged by
the Planning and Environment Department following assessment of the risk of a
Vapour Cloud Explosion at the Fuel Storage Facility.
Comment on Reason 2:
The question of waste volumes and the size of the
incinerator required to deal with the Island’s residual waste were debated at
length in P.72/2008 “Energy from Waste
Facility: establishment and acceptance of tender”.
It is as a result of the new Housing Needs Survey
published in April 2008 and the decision of the Minister of Transport and
Technical Services to increase recycling from the original rate set out in
P.95/2005 “Solid Waste Strategy” to 36%, that the annual processing capacity of
the new incinerator was reduced to the 105,000 tonne facility set out in
P.72/2008 “Energy from Waste Facility:
establishment and acceptance of tender”.
The reference made to the Minister for Transport and
Technical Services’ comment to the Environment Scrutiny Panel is entirely
correct – this comment was however made in the context of the fact that
this was unlikely, given the expected waste growth on the Island.
The Department’s position with regard to funding for
recycling has been clearly identified since the Solid Waste Strategy was
approved in 2005. The position is that the 32% target within the Strategy would
be achievable with the resources identified within the Solid Waste Strategy in
place. Additional recycling would require additional resources. The 30%
recycling rate achieved in 2007 was 3% higher than that required within the
Solid Waste Strategy. It is only through the tremendous effort that has been
placed on promoting recycling that the Island will be able to manage with a
smaller capacity incinerator, when all other factors such as migration and
number of households are taken into account.
To state that this is in stark contrast to the City of
Cardiff is somewhat surprising. Cardiff achieved a recycling rate of 20% in
2006/7, 2 years after opening its Materials Recycling Facility,
which collects all the same recyclable products that the Jersey kerbside system
collects. Had the Connétable examined the Solid Waste Strategy waste arisings
model that was made available to him as a member of the Environment Scrutiny
Panel, he would have seen the various commodities that TTS proposes should be
recycled, the rates required and when these would be achieved by.
Comment on Reason 3:
There is no denying that the cost of the new facility
is significant, but as all Members saw from the Cost Comparison Report
submitted as Appendix 2 to P.72/2008 “Energy from Waste Facility: establishment and acceptance of tender”,
all other treatment technologies, when considered as a complete package, were
even higher.
The question of opportunity cost for the land at
La Collette is valid but, as already stated, the land being used for the
new Energy from Waste facility was not originally earmarked for development. In
contrast, by releasing land at Bellozanne through the redevelopment of the
existing Energy from Waste facility, this land will be used for other
waste-related activities, thereby saving on alternative land throughout the
Island that might be required. Therefore, the lost opportunity cost against
this development is not valid.
Comment on Reason 4:
Locating the Energy from Waste facility at
La Collette has been considered in detail when studies for the development
East of Albert have been undertaken. By locating the plant in the location as
outlined and approved in P.45/2006 “Solid Waste Strategy: locations for
proposed facilities”, there is little or no impact on the proposed commercial
development of La Collette I and II reclamation sites.
When the UK Health and Safety Executive’s (HSE)
reports were issued in relation to the Buncefield explosion, a detailed Site
Specific Risk Assessment was carried out for the proposed EfW plant by the same
lead consultants who undertook the review of Buncefield and prepared one of the
reports for the UK HSE.
The report concluded that the location of the plant
did not pose an unacceptable level of risk for either the surrounding area or
the occupants of the structure.
Comment on Reason 5:
A number of extracts from the 2002 Island Plan are
provided in the report. The Connétable claims that “although the area covered
by the incinerator project does not extend into the RAMSAR site, there is a
risk that the latter will be prejudiced by the development.” This comment is
not supported by any evidence and was not raised as an issue for the Minister
for Planning and Environment when the Environmental Impact Assessment was
considered as part of the Outline Planning Application. Had any issues been
raised at the Outline Planning Stage through the public consultation process,
the Minister for Planning and Environment would have taken these facts into
account when determining the Outline Planning Application.
Comment on Reason 6:
1: Since
the Solid Waste Strategy was approved by the States in 2005, there has been
considerable opportunity for the public to influence the subsequent decisions
taken by the States in P.45/2006 “Solid Waste Strategy: locations for proposed
facilities” and P.72/2008 “Energy from
Waste Facility: establishment and acceptance of tender”.
These opportunities have been in the form of public
consultation exercises undertaken by the Department and through the formal
planning process whereby the Outline Planning Application was advertised in
accordance with protocols and the application was heard in a public meeting.
Further opportunity will arise when the public consultation on the Reserved
Matters takes place.
The statements made by the Connétable about the
assumptions used to reduce the size of the Energy from Waste facility from that
proposed within the 2005 Solid Waste Strategy are wrong. The decision to reduce
the size of the Energy from Waste facility from that proposed in the 2005 Waste
Strategy to that proposed and agreed by the States in P.72/2008 “Energy from Waste Facility: establishment and
acceptance of tender”, was as a result of increased recycling, and
reduced anticipated household growth, both of which have an impact on waste
arisings. When all of these factors were considered, the Minister for Transport
and Technical Services proposed and the States accepted the smaller capacity
plant.
The position taken by the United Kingdom government
referred to in the Connétable’s report is as a result of there being a key
driver in the UK that does not apply to Jersey – that being a requirement
to divert 65% of biodegradable waste from landfill by 2020.
Even though this legislative driver is not relevant in
Jersey, the principle being applied by the UK in terms of minimising waste
creation, re-use of products and recycling before recovering energy from waste
are exactly the same as those being applied in Jersey, the nett result being
that Energy from Waste facilities are required in both jurisdictions to deal
with residual waste. Interestingly, the UK approach includes EfW and there are
currently 18 facilities planned for implementation in the UK over
the next 2 years.
2: The
time for considering whether alternative strategies that will result in a
smaller facility has passed. This should have been done by the Environment Scrutiny
Panel and others as suggested by the Connétable before P.72/2008 “Energy from Waste Facility: establishment and
acceptance of tender”, was debated. No proven and sustainable
alternative to that proposed by the Minister for Transport and Technical Services
and accepted by the States was put forward.
3: There
can be no doubt that the existing Energy from Waste facility at Bellozanne is
amongst the dirtiest in Western Europe, as it is the only known facility
operating without any form of modern flue gas treatment. It is not only the
pollutant level from the existing plant that dictates that the new incinerator
must be built without further delay, it is the fact that the Island has no
viable alternative disposal route for the residual waste stream and the current
Bellozanne plant is in a dire condition.
The current plant is clearly at the end of its life
and without a replacement being built as quickly as possible, the Island is
jeopardising its future ability to dispose of its own waste. Delay for no good
reason would not be an acceptable argument to advance with the UK/European
authorities to seek a dispensation to export waste if the current plant fails
completely. To date, due to the continued breakdowns of the Bellozanne plant
and the chimney problems, there is over 15,000 tonnes of waste stored at
La Collette. This amount is likely to increase between now and the new
La Collette facility being commissioned. It is unlikely that the
La Collette site will have sufficient capacity to stockpile the predicted
volumes of untreated waste which cannot be burned at Bellozanne between now and
2011, therefore further waste storage sites will be required. Any delay beyond
2011, due to a public inquiry now, will only lead to the requirement to find
more sites for the Island’s waste.
Financial and manpower implications
1: The
Connétable’s report suggests a cost not exceeding £100,000 for a public
inquiry. This figure might be correct for the cost of employing an inspector to
hear and report on the principle that is being questioned for public inquiries
in the UK of waste-related projects. It does not, however, in any way address
the other very significant costs that will result from this delay.
2: The
tender sum for the Energy from Waste contract expires on 31st October 2008.
After that time, various assumed rates for currency, labour and materials
within the contract are permitted to increase in line with publicly available
indexes. Details of these delay costs are commercially confidential, but the
expected impact at current indexing rates are in the order of £800,000 per
month. The Connétable suggests that an inquiry will be complete by the spring,
which will result in a 4–6 month delay which equates to between £3.2 and
£4.8 million at current rates. This also assumes that the contractor
remains willing to delay commencement of the works and does not withdraw from
the contract to pursue better opportunities elsewhere, as the Contractor is
entitled to do after the end of October 2008 and a number of the earlier tenderers
to the contract have already done. If this were to happen, the delays
associated with re-tendering and re-negotiating, together with the costs
associated with buying a new facility in what is rapidly becoming an overheated
market, are likely to rise significantly beyond the figures currently approved.
3: The
delay will result in more waste from Bellozanne having to be stockpiled at
La Collette, resulting in more land being taken up, more specialist pits
being constructed at a cost of approximately £80,000 and £100,000 each. In
addition, significant additional resource will be required to haul the waste
and stockpile it from Bellozanne to the pits at La Collette.
4: The
environmental impact of storing tens of thousands of tonnes of waste in pits at
La Collette will be significant. Given that complaints from the Havre des
Pas residents in connection with the current compost operation are already
considered unacceptable by the Connétable and some other St. Helier
Deputies, it is inevitable that further nuisance will be caused if tens of
thousands of tonnes of additional waste are having to be stored for a number of
years.
5: Members
are urged to reject this proposal for a public inquiry on the grounds that all
of the issues that would be considered through an inspector’s inquiry have
already been considered and addressed by the Assembly throughout 3 debates
over a period of 3 years.