STATES OF JERSEY

COMMITTEE OF INQUIRY: Energy from Waste plant procurement process (P.139/2008) – comments
Presented to the States on 14th October 2008
by the Minister for Transport and Technical Services
STATES GREFFE
COMMENTS
Executive Summary
All key questions raised in the proposition are
addressed in this response.
Contrary to Deputy Baudains’ inference, the OJEC
(Official Journal of the European Community) process is the most fair and open
process for large-scale procurements in the European context.
The OJEC notice issued in relation to the procurement
was not unduly restrictive as was evidenced by the Expressions of Interest
received, which included many alternative technologies.
There was no bias in favour of incineration –
instead an open and fair appraisal of all waste treatment technologies was
carried out throughout the procurement process.
The process took full account of trends in waste
management as evidenced by the decision by the Minister for Transport and
Technical Services to reduce the capacity of the plant in the light of latest
information.
A full and rigorous appraisal was undertaken by
Transport and Technical Services throughout a lengthy procurement process to
demonstrate value for money, as evidenced by the Cost Comparison Report
appended to P.72/2008 “Energy from
Waste Facility: establishment and acceptance of tender”.
The other assertions made by Deputy Baudains in his
accompanying report are factually incorrect and refer to facilities that would
not meet the specification required to deal with Jersey’s waste.
Members are therefore urged not to support this
proposition as the questions have already been debated several times, or are
addressed within this response.
(a) Was
OJEC Notice the most appropriate way to encourage Expressions of Interest?
Deputy Baudains appears to be questioning whether one
of the most widely used procurement routes in Europe was the most appropriate
way to attract the waste industry to Jersey. The OJEC notice has been in use
within EU member states since 1952 and is used not only for major construction
projects, but for many other forms of large-scale, competitive procurement
routes such as bus and train franchises and major supply contracts.
The question whether this was the most appropriate way
to encourage Expressions of Interest from major European suppliers of waste
treatment technology is refuted, as it is so widely used by industry and is
recognised as giving all potential suppliers a fair and open opportunity to put
their companies forward for new projects.
(b) Was
the OJEC Notice issued unduly restrictive?
The wording of the OJEC notice issued in August 2003
was only agreed by the Public Services Committee after several revisions and
detailed input from Deputy Duhamel who was a Committee member at that time.
Within the notice, there are 2 key paragraphs which
set out the purchaser’s requirements and for clarity, these are printed below.
II.I.6 Description of Plant
Design, supply, construction,
installation, commissioning and testing of an Energy from Waste Plant.
The Plant is to have two streams or
processing lines each capable of processing approximately 10 tonnes of
waste per hour, with power generation. The waste to be processed will include
municipal, industrial and commercial waste including for example shredded bulky
items, tyres and dried sewage sludge.
III.2.1.3 Technical Capacity – Means of Proof Required
It is essential that the contractor
is capable of designing, constructing and commissioning a suitable plant able
to meet the process demands using a proven technology. Details of the
technology proposed are to be submitted. A reference list providing details of
similar installations of equivalent capacity that have been successfully
completed by the contractor should be provided as evidence, along with details
of the technology to be used. As a minimum, details including waste type,
capacity and actual annual throughput shall be provided for two plants of a
similar size, using the same technology, processing similar wastes, that have
been in operation for two years.
From the above description it is clear that the
Committee was requesting an energy from waste solution, but it was not
prescriptive in any way about what form this process should be.
Some Members might mistakenly consider that an Energy
from Waste plant means an incinerator of conventional design, but in industry
terms, any form of waste treatment operation that creates energy in the form of
electricity or heat from a waste source can be classified as energy from waste.
For example, anaerobic digestion of organic waste produces methane gas, which
is then used to produce energy in the form of electricity or heating water for
process plant, etc. The same can be said for many other ‘alternative
technologies’ that have been promoted over the past decade.
Irrespective of this definition, the waste treatment
industry clearly did not view the 2002 OJEC notice as being too restrictive, as
9 Expressions of Interest were received, which included anaerobic digestion,
gasification and pyrolosis, autoclaves as well as conventional moving grate
incineration technology.
(c) Was
there a bias in favouring incineration against alternative technologies?
It is clear from the original Expressions of Interest
that the wording of the OJEC notice did attract alternative technologies. The
procurement process then considered whether these technologies complied with
paragraph III.2.I.3 of the OJEC Notice in that they could demonstrate they
were proven technology, operating 2 reference plants of similar capacity to the
Jersey requirement for 2 years on similar waste.
Throughout the various discussions with the Shadow
Scrutiny Panel and the main Scrutiny Panel and in the States debate, very few
States Members have ever spoken against these criteria as being an appropriate
safeguard for Jersey given that there is no alternative way of processing waste
if the plant fails to perform.
Members will recall that during the Solid Waste
Strategy debate (P.95/2005), the President of the Environment and Public
Services Committee gave an assurance to Members that a report would be
published outlining all of the conventional and alternative technologies
considered and whether they were appropriate for Jersey.
The initial Babtie Fichtner Technology Review Report,
published in October 2005, considered 59 technologies and was circulated
to all States Members. It was updated to include all of the technologies that
had been put forward by companies for consideration by Transport and Technical
Services since the original Technology Report had been completed and re-issued
to States Members prior to the debate of P.72/2008: Energy from Waste Facility: establishment and acceptance of tender
as P.72/2008 Add. The updated Technology Review Report concluded that,
although several new technology companies have emerged onto the market since
2005, none are sufficiently proven or have offered a viable solution for the
whole of the Jersey waste stream.
(d) Did
the procurement process take account of the trends in waste management in light
of expected lifespan of the plant?
The original plant capacity of 126,000 tonnes per
annum set out within the Solid Waste Strategy 2005 was designed having taken
into account the waste composition on Jersey, a recycling target of 32% and the
predicted number of households anticipated over the life of the plant, based
upon information used to inform the Island Plan 2002 and the outcome of the
Housing Needs Survey 2005.
Having regularly reviewed the trends in waste
management since 2005 and, having taken into account the good public response
to recycling, coupled with the reduced growth in household numbers, anticipated
within the Housing Needs Survey 2007, the Minister for Transport and Technical
Services agreed to reduce the size of the proposed Energy from Waste plant and
increase the recycling target to 36%. This matter was fully considered by
States Members when debating P.72/2008.
Whether a new and innovative technology will come to
the market within the 25 year life of the plant that will radically change
the way in which Jersey, the UK and Europe manage their waste is not possible
to predict.
However, despite the £30 million invested by the
UK government to review and promote alternative technologies in 2003 under its
New Technologies Demonstrator Programme, it is clear that while some new
technology suppliers have benefited from the investment in certain
conditions, no new technology types have emerged beyond those already
considered within the procurement process.
The majority of new plants being specified in the UK
call for conventional moving grate technology. All of these plants will have a
20-25 year lifespan. Given the outcome of the UK New Technologies
Demonstrator Programme, the requirement for Jersey to have proven technology
and the lack of any new technology type emerging in the market that has been
proved, the procurement process undertaken is considered robust.
(e) What
steps were taken to ensure that the new plant represented best value for money?
When the States considered and approved P.72/2008 “Energy from Waste Facility: establishment and
acceptance of tender” Members were provided with, as an Appendix to the
Report and Proposition, a Cost Comparison Report that considered alternative
technology options for Jersey. It was clear that the preferred solution of
realistic recycling with an Energy from Waste facility for treatment of
residual waste, provided the best value when all capital and revenue costs had
been accounted for over the 25 year life of the proposed facility.
Deputy Baudains’ report, accompanying the Proposition,
makes specific reference to one supplier who did not respond to the original
OJEC notice and who has never contacted the Department or their technical
consultants in relation to the Jersey project. Deputy Baudains’ report also
contains some factually inaccurate statements which need to be addressed.
(i) Deputy
Baudains states that countries are moving away from mass-burn conventional
systems to new technologies.
In
the UK there are many major waste projects progressing to enable Councils to
meet their obligation of achieving the European Landfill Directive target of
reducing the amount of biodegradable waste sent to landfill to 35% of 1995
levels. The driver for the UK and Europe is reducing the creation of greenhouse
gases from organic waste decomposing in landfill, which is very different to
Jersey’s requirement. However, mass-burn “energy from waste” plants remain the
leading process that other jurisdictions are choosing to meet their Landfill
Directive targets.
Throughout
Europe, there are numerous examples of mass-burn energy from waste plants being
installed – it is not an outdated technology. In most countries these
plants are being used to burn residual waste, that is, the waste remaining
after sensible levels of recycling, exactly as proposed for Jersey. However,
the technology most widely-used is the well-proven grate, or so-called
“mass-burn” technology. It should be noted that the technology supply company
highlighted by Deputy Baudains has supplied many plants to burn waste, and the
vast majority of these are the same grate based “mass-burn” solutions which he
claims countries are moving away from.
(ii) Deputy
Baudains states that a world-renowned firm willing to supply a plant for
£68 million was “put off” by the Transport and Technical Services
Department’s consultants.
This
is an inaccurate statement. The technology supply company referred to by Deputy
Baudains have never contacted Transport and Technical Services or its
consultants with regard to the Jersey project. An intermediary company who
claimed to have the rights to represent this main technology supply company has
contacted the Department on a number of occasions throughout a 4 year
period. This intermediary never took up the offer of a meeting with TTS to
understand the overall requirements of the project and did not submit a formal
Expression of Interest to prompt consideration within the pre-qualification
process, and at no time provided anything more than a 2-3 page e-mail
outlining how it could provide a solution for the quoted £68 million.
In
order to assess the true and accurate position as regards the main technology
supply company, who are very well-respected in the waste industry, their Sales
Director was contacted directly by the Transport and Technical Services
Department’s technical consultants to ascertain their precise involvement.
Their response confirmed that they had passed information to the intermediary
company relating to 2 of their plants built in Sweden. A simple investigation
carried out by an Internet search of the 2 named plants identified that
the main comparison plant was in fact designed to burn fuel based primarily on
virgin wood and waste wood chip. It has also been designed to burn
refuse-derived fuel (RDF). From information on the technology supplier’s
website, it appears that their scope of supply for this single-stream plant was
for the fuel-handling system, combustion grate, boiler and control system only.
There is no reference to the electrical generation equipment, waste sorting
facility to produce Refuse-Derived Fuel or the many other major infrastructure
requirements or the main building to house such a facility.
The
response from the main technology Supply Company Director states “... we
are unaware of the content of the tender material for Jersey, and have no
information that may justify whether these costs (the £60 million quoted
within Deputy Baudains’ proposition) are applicable for the Jersey project.”
The
Director of the Main Technology Supply Company goes on to state that there is
no consortium led by his company for the Jersey project, but he was aware that
the intermediary company had investigated the cost of supplying a mechanical
biological treatment plant (MBT) that would provide a fuel source that would in
turn be fed to one of their mass-burn plants.
The
main technology supply company would be seen as a direct competitor to the
successful preferred and reserved bidders for the Jersey project, as their
facilities would be of a similar size to the new Jersey plant. The installed
technology and flue gas treatment plant would be broadly the same which
suggests, for a 2-stream plant with all of the associated infrastructure, their
price would not have been dissimilar to the tenders received. There would of
course be significant additional capital and operating costs due to the
additional waste processing plant which would produce the refuse-derived fuel.
This plant would also generate other waste streams which would require
disposal, as the refuse-derived fuel consists normally of the paper and plastic
fraction of municipal waste, typically only 40-50% of the incoming waste. No
mention is made of how the Island would dispose of the remaining waste rejected
from the refuse derived fuel.
It is
therefore extremely difficult to see how the intermediary company could offer
any form of accurate price without knowing the Jersey specification and only
having corresponded by e-mail.
Deputy
Baudains states that he contacted the main technology supply company that had
been asked to supply an old-fashioned plant (albeit against their better
judgement).
This
company have never been asked to provide a plant via Transport and Technical
Services or their consultants. Therefore, to imply they had been asked to
supply an old-fashioned plant is simply misleading.
Deputy
Baudains asks why Jersey has committed £102 million when the same plant
(by a firm which has built hundreds of them) could have been supplied for
£60 million.
Deputy
Baudains fails to recognise that the total price for the Jersey project is for
a 2-stream facility and includes enabling works such as new road access,
connection to the Jersey Electricity Company chimney and cooling water system
and professional fees, etc. In addition, the new facility at La Collette
will include a new refuse pre-treatment plant and landscaping to the area, none
of which appear to have been factored into the Deputy’s calculations.
From
the above examples it is clear that Deputy Baudains has only been in possession
of part of the facts, and both he and the intermediary company have completely
failed to take steps to fully understand the scope of the supply for the Jersey
project. It is clear that the main comparison plant mentioned in the Report and
Proposition is very different in scale and operation to that proposed for
Jersey.
Conclusions
All key questions raised in the proposition have been
addressed in this response.
A full and rigorous appraisal was undertaken by
Transport and Technical Services throughout a lengthy procurement process. This
was overseen by political representatives on the Solid Waste Strategy Steering
Group and a Project Board in full compliance with the States Standing Orders.
The evaluation process has been subject to review by
the States Internal Audit function who confirmed that the financial advice was
consistent with best practice and sufficient to provide an adequate basis for
the assessment of tenders and financing options.
The assertions made by Deputy Baudains in his
accompanying report are factually incorrect and where he has referred to
alternative plants, the pricing information he has obtained refers to
facilities that would not meet the specification required to deal with Jersey’s
waste. Comparing a single-stream wood-burning plant with no pre-treatment
facility to the Jersey requirements of dealing with municipal and commercial
waste is simply inappropriate and misleading to Members.
Members are therefore urged not to support this
proposition as the questions have already been debated several times, or are
addressed within this response.
Financial and manpower implications
The cost for a Committee of Inquiry is likely to be
significantly higher than those proposed by Deputy Baudains. A consultant or
specialist with the requisite knowledge to understand the waste industry is
unlikely to be available for less than £1,000 per day, not including travel and
accommodation expenses. When these costs are taken into account, the time
available for a specialist to do the necessary research, attend public hearings
and then provide a detailed response would be extremely limited and unlikely to
be achieved within the budget proposed by Deputy Baudains. In addition, the
costs for Committee Clerks and support, etc., are not shown.